I noticed that the Thanksgiving Point Driving Range was under construction yesterday, May 10th, 2016. I was curious if they were allowed to start excavating the site, so I sent the following two emails to Kim Struthers, Ryan Woods and Mayor Bert Wilson at the City of Lehi, UT. I will await their response if any. Below the two emails are a GRAMMA request I am putting in with the City today requesting documents that were required to be submitted by the LDS Church prior to them receiving the grading permit. I will see if the City and the Church are adhering to the code word for word, exactly as it is written or if they are ignoring all kinds of provisions within the code for the LDS Church.
The Code is the Code and everyone must abide by the code.
Lets see what the city comes back with.
From: William Conley <billhytek@hotmail.com>
Sent: Tuesday, May 10, 2016 5:22 PM
To: Ryan Wood; kstruthers@lehi-ut.gov; Bert Wilson
Subject: Permit
Sent: Tuesday, May 10, 2016 5:22 PM
To: Ryan Wood; kstruthers@lehi-ut.gov; Bert Wilson
Subject: Permit
Gentlemen
I just spoke with both the
building department and public works department. Public works indicated
that Sunroc would not be out their grubbing (grading) without a permit.
It appears that the permit for grading was issued by the city. The
building inspectors indicated that they received a building application on May
3, 2016 and it is in line to be approved.
Is this allowable? Please
respond back.
Bill Conley
First email, this one I
sent with a number of pictures (above) I had taken of the grubbing.
From: William Conley <billhytek@hotmail.com>
Sent: Tuesday, May 10, 2016 4:18 PM
To: kstruthers@lehi-ut.gov; Ryan Wood; Bert Wilson
Subject: Pictures
Sent: Tuesday, May 10, 2016 4:18 PM
To: kstruthers@lehi-ut.gov; Ryan Wood; Bert Wilson
Subject: Pictures
Ryan and Kim
I noticed that the
Thanksgiving Point driving range is being scrubbed today by a SunRoc
employee.
Has the LDS Church been
issued a building permit?
Can the LDS Church begin
excavation while there is an appeal pending? What happens if they lose
the appeal? What happens if I lose the appeal and take it to court? I am
a little concerned the LDS Church has begun excavating the property.
Could you please reply to
this email and let me know, if the LDS Church has been issued a building permit
and secondly, are they permitted to begin excavating the property while there
is an appeal pending?
Bill Conley
801 867 7227
Gramma
Request exhibit 1
Section
28.060 Procedures for Establishment of Resort Community Zone
D. Effect of Area
Plan Approval. If a proposed
Area Plan is adopted by the City
pursuant to Chapter
15of this Code, all permits,
licenses and development
must comply with the adopted Area
Plan. Additionally,
developers
and builders must comply with the Lehi City
General
Plan, the Lehi City Development Code, and all
other
codes and ordinances of the City unless modified
by the adopted Area Plan.
Request: If any of the development codes have been modified by this
area plan, please provide me a copy of the modification and date of
modification.
Request: Please provide me with a copy of the Application for
Grading Permit submitted to the city by the applicant. Please provide me with
ALL documents (as required by the application) submitted by the applicant with
the Grading Permit Application.
Request: Please let me know when you have gathered all the
documents in the GRAMMA request and I will come and view them at City Hall.
Failure to provide ALL the documents required in this GRAMMA request
will be viewed that the applicant has not provided ALL the required documents
to the city, which is a violation of the Lehi Development Code and the grading
permit should not have been approved.
Section 12-B.020 Grading
Permit Requirements
(Amended 11/12/13)
A. A grading permit is required
for a project involving any of the following:
1.
Any grading,
clearing, or grubbing in excess of one (1) acre, (43,560 square feet). Clearing
includes the felling or removal of trees, shrubs, or other native material when
the ground has been disturbed in excess of one (1) acre.
Request: Please verify in writing to me that the grading application is
complete and provide me a copy of the minutes of the each of these recorded
meetings by each of the reviewing committees who spent time reviewing the
grading application. Including; dates, times, those in attendance and what was
discussed. See section below relating to
this requirement. Please provide the schedule showing that the grading permit
was placed on the reviewing department’s schedule. See code below.
C. Grading permit applications
shall be submitted to the Lehi City Planning Department.
1.
Once the
application has been deemed complete, the grading permit application shall be
placed on the Reviewing Departments agenda for consideration.
Request: Please provide proof that (1) the grading application was
review by the reviewing departments, (2) that the grading application was heard
before the planning commission which included a public hearing, (3) that the
grading application was heard before the city council which included a public
hearing. See code below.
2.
Grading Permits
for grading projects with more than ten (10) contiguous acres MAY be issued by the Public Works
Director following review by the Reviewing Departments, review and
recommendation following a public hearing by the Planning Commission and review
and approval following a public hearing by the City Council.
(a) When considering the
approval of the grading permit the Public Works Director, Reviewing
Departments, and (when applicable), Planning Commission and City Council, will
verify that all of the following criteria are met (in addition to other
applicable requirements of this code and other city codes):
(i)
Approval of the
proposal will not pose a threat to or be detrimental to the public health,
safety, and welfare, nor be materially detrimental to fish and wildlife habitat
and/or water resources as determined by an expert consultant.
Request: Please provide an expert
consultants opinion provided with the grading permit supplied by the applicant
that the Thanksgiving Point Golf Couse Driving Range which is located a few
hundred feet from the Jordon River is not detrimental to the public health,
safety and welfare nor is it materially detrimental to the fish and wildlife
habitat and or water resources.
F. Upon COMPLETION of the above, the grading permit will be issued. The
grading permit along with the approved grading plans and the SWPPP must be kept
on site through the duration of the grading project.
Request: Please provide me the location of the grading permit
application on site so that I may verify that it is ALWAYS on site.
BEFORE THE WORK BEGINS
(REQUIRED, MUST, ABSOLUTE, SHALL) AND AFTER THE BOND HAS BEEN POSTED, A
PRECONSTRUCTION CONFERENCE CAN BE HELD.
Request: Please provide me a
copy of the bond that has been posted by the applicant. Please provide me with
the date, time and those in attendance of the preconstruction meeting. Please
provide me with the minutes to that recorded meeting. See code below.
Section 12B.060 Grading
Permit Administration
(Amended 11/12/13)
A.
Before work
begins on a grading project and after the bond is posted the Public Works
Director will hold a preconstruction conference. The approved grading plans
will be issued at this conference.
Request: Please provide me the name of the person from the Streets
Department who is responsible for inspecting and monitoring the following. (I will be following up with him to make sure
the following items are being adhered to)
1. Grading is done only in the
designated survey area.
2. Monitoring the approved
extent and depth of the grading (both horizontally and vertically).
3. Verification that all
required reports are submitted to the City. Reports must include daily logs of
real-time data, and may be requested by the inspector weekly or daily if needed. (
I will be following up and seeking a GRAMMA request daily or weekly if needed)
4. Reviewing the daily truck
trips and the week-ly calculation of daily trip averages as outlined in
12-B.040 B. The effective capacity of each truck must be specified on every
report.
5. Designated haul routes are
being used and that safe hauling practices are being followed.
6. Reviewing a volumetric
survey provided by the landowner or his/her designee, using a mutually agreed
upon method, monthly.
Request: Please provide me with a document showing where the survey
stakes for the grading are located. I
have been to the site and can’t seem to find the survey stakes. This is a violation of the code. See code
below:
Section 12-B.080 Grading
Permit Violations
(Amended 11/12/13)
A grading project will be
deemed in violation if any of the following occur:
B.
Removal of survey
stakes and/or not maintaining clearly marked survey stakes.
Make sure the applicant has survey stakes maintained at all times. See code below:
Section 12-B.090 Penalties
(Amended 11/12/13)
C.
The same rules
apply for removal and maintenance of survey stakes
D.
D. Any person
who is found to be in violation of an approved grading permit, or who is found
to be in violation of this Code, may be charged with a misdemeanor and subject
to enforcement by the City, as per Section 34.010 of this Code.
Request: Please provide me
with a copy of the following required documents provided by the Applicant (LDS
Church, Trio or VCBO) to the City for the Family Search Project on the
Thanksgiving Point Golf Course.
Section 12-B.040 Grading
Permit Submittal Requirements (Amended
11/12/13)
An application for grading
permit shall include the following:
A. A narrative outlining the
project. The narrative must include a reason grading is required.
B. A re-vegetation plan must be
provided for any disturbed land, including slopes created by grading, and any
vegetation that will remain. The following provisions shall also apply:
1.
Conserve topsoil removed during construction for later use on disturbed areas
as needed, and as approved by the City.
2.
All disturbed soil surfaces shall be stabilized before final acceptance of the
development by the City. Stabilization shall include, at a minimum, six (6)
inches of topsoil and native seed mix or other suitable treatment.
3.
Native seed mix and the process of application shall be approved by the City.
4. In all areas under ownership
and control of the Developer, the Developer shall be fully responsible for any
destruction of native vegeta-tion required to be retained, and shall be
responsible for replacing destroyed vegetation.
C. A general vicinity map of
the proposed site.
D. A meets and bounds
description of the proposed grading site is required. The description must be
submitted in hard copy and electronically, in a for-mat acceptable to Lehi
City. The property limits and accurate contours of the existing ground must be provided.
E. A map of the subject area
showing the elevations or finished contours to be achieved by grading
And the boundaries of the
grading site as required by subsection D above. The map should show
representative depth of cuts/fills on the grading plan, as well as any critical
or sensitive lands as identified by Section 12.060 (J) (K) of the Lehi City
Development Code. It should also include the specifications and recommendations
on any associated soil compaction of the site.
F. The amount of material to be
moved and/or re-moved must be provided. Extractable volumes must also be
provided in both bank cubic yards (BCY) and loose cubic yards (LCY). Where
applicable, in fill areas, compacted cubic yards (CCY) must be provided. The
number of estimated total truck loads and the estimated number of truck loads
per day must be provided.
G. A completion date must be
provided. In no case can a grading permit be approved for a timeframe greater
than one (1) year; however an extension may be requested if the project is not
completed within the approval timeframe. All extensions shall be as per Section
10.120 of the Development Code.
H. The main haul route shall be
outlined and shown on a map. A secondary haul route may be required when
determined necessary. Haul routes should avoid school zones, and any areas of
potential conflict where possible. The number of ex-pelted daily trips shall
also be indicated. Haul routes for
projects greater than ten (10) acres must be approved by the City Council
This project is more than 10 acres.
Please provide me with a document whereby the City Council approved the
grading permit. Date and time of the City Council meeting and those in
attendance.
I. A plan showing the locations
of retaining walls in excess of four (4) feet.
J. A map of the subject area
showing the location and type of erosion and sedimentation control devices.
Some erosion is unavoidable. The resulting sediment must be trapped on the
site, even during de-sign flood conditions. Construct sediment fences and
sediment traps and basins before other land-disturbing activities occur.
Sediment fences, traps, and basins must be properly maintained, regularly
inspected, and cleaned as necessary. Dispose of the sediment removed during
cleaning in a place where it will not flow back into the control structure.
Con-sider the maintenance and repair costs of each erosion control practice
before construction. Erosion and sediment control structures should be
inspected and maintained. If not properly maintained, some practices may cause
more damage than they prevent.
K. A written statement and or
plan addressing the following provisions:
L. No person shall block,
impede the flow of, alter, or construct any structure or deposit any material
or commit any act which will affect normal or flood flow in any stream or
watercourse without first obtaining a permit from the appropriate agency.
M. All engineering work shall
be approved and stamped by a licensed professional engineer who can demonstrate
experience in geotechnical or geological sciences.
N. The landowner or his/her
designee will be required to post a bond for all restoration of graded areas.
The bond will cover the cost of needed reclamation, at a minimum the cost of
topsoil, seeding, and erosion control measures. The bond must be placed in accordance with City bonding procedures as
per Sections 11.220 and 11.320, Guarantees and Bonds, of the Lehi City
Development Code.
O. A current Storm Water
Pollution Prevention Plan (SWPPP) and a Utah State Notice of Intent (NOI) will
be submitted and maintained during the permit period.
P. Any grading near waterways will require a Stream Alteration Permit
from the Utah Division of Water Rights, and a copy of that permit must be
submitted with a grading application.
Jordon River is near.